PIPING & MECHANICAL

Industrial Mechanical Construction

Equipment setting for pumps, compressors, exchangers, vessels, and skids, plus the piping and bolted joints that tie them in.

Set & Tied In

equipment plus connecting piping

All Equipment

pumps, compressors, exchangers, vessels, skids

Turnarounds

and outage work

0.0

TRIR and DART rate

Equipment Set, Piped, and Ready for Turnover

Setting equipment is only part of the job. It still has to be piped, bolted, and documented before it can run. Spector Services sets pumps, compressors, exchangers, vessels, and skids, then installs the piping and makes up the bolted joints that tie them in.

Alignment, grouting, and hot taps are handled through qualified subcontractors and coordinated inside our scope, and cranes are rented to match each lift. We work new installations and turnaround and outage scopes, as prime contractor or subcontractor.

What We Set

Spector crews handle equipment setting and the work that ties it in.

  • Pumps
  • Compressors
  • Heat exchangers
  • Vessels
  • Skids
  • Connecting piping and bolted joints
  • Coordination of alignment, grouting, and hot taps
Crew member running pipe fusion equipment on large-diameter pipe in an excavation

Capabilities at a Glance

Equipment

Pumps, compressors, exchangers, vessels, and skids.

Piping

Connecting piping in every material and size, welded to qualified procedures.

Bolting

Joint assembly following ASME PCC-1, with flange tagging and torque reports.

Specialty Work

Alignment, grouting, and hot taps through qualified subcontractors.

Lifting

Rental cranes sized to each project’s lifts.

Delivery

Prime contractor or subcontractor, on new installations, turnarounds, and outages.

How We Deliver Mechanical Work

STEP 1

Review the Package

We review equipment data sheets, foundation drawings, and piping isometrics before pricing, so questions get answered at bid time instead of in the field.

STEP 2

Plan Lifts and Sequence

Lifts, crane rentals, and installation sequence are planned around the site and schedule.

STEP 3

Set the Equipment

Equipment is set on its foundations, with alignment and grouting coordinated through qualified subcontractors.

STEP 4

Pipe and Bolt Up

Connecting piping is installed and welded, and bolted joints are made up following ASME PCC-1.

STEP 5

Test and Turn Over

Systems are tested, and weld maps, torque reports, and flange maps go to you with the equipment.

Safety You Can Verify

Equipment setting puts crews under heavy lifts and next to operating systems. Here is the record Spector Services brings to it.

0.0 TRIR and DART

No recordable injuries and no days-away, restricted, or transferred cases.

A Grades

Rated A on both ISNetworld and Veriforce.

Dedicated Safety Personnel

Safety staff dedicated to Spector’s field operations.

Site-Ready Crews

Field crews carry TWIC cards and Safety Essentials/Basic Plus training.

What to Send for a Mechanical Bid

A complete package gets you a faster, tighter number. Send what you have, and we will ask for anything else we need.

  • Equipment list and data sheets
  • Foundation and anchor bolt drawings
  • Piping isometrics and tie-in points
  • Lift weights and crane access
  • Alignment and grouting requirements
  • Turnaround or outage windows and schedule

FAQ

Mechanical Construction Questions

Quick answers for owners and general contractors planning equipment installations. Have a question that isn’t covered here? Talk to us directly.

Pumps, compressors, heat exchangers, vessels, and skids.

Planning an Equipment Installation?

Send the equipment list, data sheets, piping drawings, and schedule. We will review the package and follow up with questions or a bid.

Scroll to Top